F14P4 Overall Progress
5
100%
11/20 F/E tool
Plan 98.40% move-in Special
11/24 100%
10/13 Fab BEOL One-sigma Report
FFU turn-on matching
80%
Actual 98.25%
8/16 clean room 11/10 B/E tool 特別
move-in
installation start 企劃
60%
7/8 Fab topping ceremony; Fab
L20 east side RC slab complete; 9/15 clean room air
HPM RF &L40 RC slab complete pressurization
40%
6/8 Fab LRF & L40, 8/30 Fab building
5/31 Fab steel HPM L30 RC slab watertight
erection complete complete
8/21 Fab L30 waffle
20% 4/29 Fab steel slab complete
erection start
2/8 piling start 6/29 HPM steel
6/8 HPM steel erection complete
erection start
0%
02-08 02-22 03-08 03-22 04-05 04-19 05-03 05-17 05-31 06-14 06-28 07-12 07-26 08-09 08-23 09-06 09-20 10-04 10-18 11-01 11-21 11-15 12-01 11-29