Page 19 - Vol.06
P. 19

●   Case 5: IPI with centralized/inner-fab RCW
                                                                      tanks, without the use of cross-fab pipeline








                Figure 3 shows the superstructure for a receiving tank,
              like a buffer where the wastewater is held before being sent   Finally, the objective shown in Eq. (19) is to
              to treatment systems. The water balance for each receiving   minimize the freshwater consumption. Besides, the
              tank is given in Eq. (12). It is worthy of mention that effluent   design problem is a mixed-integer nonlinear program
              treatment is quite important for environmental concern, but   (MINLP) for the binary variables and bilinear terms.
              this part is omitted and kept for future work


                Equation (13) defines the lower and upper limits to the
              connecting flow rates with the use of binary variables. y*=1   Results
              denotes the existence of the connection between *.
                                                                         he example with fifteen water-using units
                                                                         divided into three individual fabs (each adapted
                                                                   Tfrom Wang et al., 2003, Example 2; Zheng et al.,
                So far, the aforementioned equations constitute a basis   2006, Case study 2; and Gunaratnam et al., 2005, Case
              for inter-fab water integration, as a general case of hybid   study 1) is provided to illustrate the application of the
              design options. For convenience, the equations are grouped   proposed formulation. The solution tool is the General
              to a set Ω 0 ≡{Equations (1)-(13)}. Five integration schemes   Algebraic Modeling System (GAMS, Brooke et al.,
              are considered in this work, as described below: (Note: IPI   2003), and the solver for MINLP is BARON.
                                                   cen
              =inter-fab integration; p=index for fabs; M cen  and M  are sets   In case 1, without any inter-fab integration, the
              of centralized and inner-fab mains).
                                                                   respective freshwater consumptions of individual fabs
              ●  Case 1: No IPI without using RCW tanks:           are 111.81 ton/h, 111.83 ton/h and 183.59 ton/h, with a
                                                                   total amount of 407.24 ton/h. In case 2, inner-fab RCW
                                                                   tanks are put in each fab to enhance the operability,
                                                                   but the mixing effect increases the overall freshwater
                                                                   consumption from 407.24 ton/h to 421.82 ton/h. In case
              ●  Case 2: No IPI with inner-fab RCW tanks
                                                                   3, direct IPI is carried out and the overall freshwater
                                                                   consumption is reduced from 407.24 ton/h to 354.46
                                                                   ton/h in comparison with case 1. However, direct IPI
                                                                   would be hard to operate for control problems and
                                                                   the network complexity. Therefore, indirect IPI is
                                                                   performed in case 4. Although the overall freshwater
                                                                   consumption is slightly increased to 355.54 ton/h
              ●  Case 3: direct IPI (Chew et al., 2008)            because of the mixing effect, the network structure
                                                                   will be simpler. For some larger scale problems,
                                                                   centralized RCW tanks would be employed in addition
                                                                   to inner-fab mains for practical needs so case 5 is to
              ●  Case 4: indirect IPI (Chew et al., 2008)
                                                                   be examined. The freshwater consumption is slightly
                                                                   increased to 362.1, but the operability of the whole fab
                                                                   can be improved when compared to cases 3 and 4. The
                                                                   resultant network configurations for cases 2 and 5 are
                                                                   shown in Figs. 4 and 5, respectively.








                                                                              NEW FAB TECHNOLOGY JOURNAL         APRIL 2012  19
   14   15   16   17   18   19   20   21   22   23   24