                                 F15A

                     F15B







                   Figure 2、The TCZWM Site Location            Figure 5、The front view of TCZWM campus from Keya Seven Road





















                    Figure 3、The TCZWM Mater Plan               Figure 6、The projected interconnecting pipe racks


                                                             4.  The Design of Six ZWM Plants

                                                             4.1  IPA Regeneration Plant(IRP)

                                                             4.1.1  Plant Scope

                                                                 IRP will process about 27,600 tons/yr of IPA waste feed
                                                             and generate about 2,520 tons/yr of electronic grade of
                                                             IPA product back to TSMC for raw material use. The Table 2
                                                             demonstrates the typical concentration and impurities of waste
                                                             IPA feed.
                 Figure 4、The top view of TCZWM campus


                               Table 2、The Typical Concentrations and Impurities of Waste IPA Feed.