HT-SPM的標準處理設備(BOM表)。後續本團隊將持續評估
Wet-EP用於處理其它製程廢氣的可行性及效益。
參考文獻
[01] Parsons, M.T., Knopf, D.A., & Bertram, A.K. (2004). Deliquescence and
crystallization of ammonium sulfate particles internally mixed with
water-soluble organic compounds. J. Phys. Chem. A, 108(52), 11600-
11608.
圖6、Wet-EP PRE : 理論vs.實際測值 [02] Chang, C.L., & Bai, H.(1999). An experimental study on the
performance of a single discharge wire-plate electrostatic precipitator
with back corona. J. of Aerosol Sci., 30(3), 325-340.
[03] Xiao, L., Zhang, M. and Wang, Y.(2018). Study on collection of the
4.3 煙道採樣分析
particles in waste gasification gas by wet electrostatic precipitator.
煙囪採樣的結果顯示,在HT-SPM(JDCRSH)下游改以 Adv. Eng. Res., 170, 1578-1585.
[04] Lin, G.Y., Chen, T.M., & Tsai, C. J. (2012). A modified deutsch-anderson
Wet-EP後,煙道VOC0102、VOC0304、及VOC0506(F12P6採 equation for predicting the nanoparticle collection efficiency of
兩台轉輪共管一煙囪之設計)之硫酸年排放量分由0.51、0.14及 electrostatic precipitators. Aerosol Air Qual. Res., 12(5), 697-706.
0.21ton/year降低為0.29、0.12及0.20ton/year,共降低了0.24
ton/year,如 圖7所示。進一步採樣及分析VEX煙道及硫酸的 作者介紹
來源後發現,VOC下游機台的硫酸用量約有99%的供應到HT- 林尚志 S.C. Lin
藉由Hook up、LSC、SP1、AAS一條龍多年經驗找出問題
SPM製程。目前為止,本廠區仍有4台HT-SPM未改善,因此
點,以最佳的方法徹底改善PM 2.5 的問題。
若是全部改以Wet-EP處理該製程的廢氣大幅減少硫酸的排放
並解決PM 2.5 的問題。 田麒鈺 C.Y. Tien
國立交通大學環境工程研究所碩士。
國立交通大學環境工程研究所博士。
2021台積電廠務處工程師。
圖7、煙囪採樣結果
5. 結論
本團隊於2020年導入Wet-EP並應用於處理HT-SPM製程
產生的廢氣,並評估及分析VEX煙囪硫酸氣體過高的原因。
結果發現主要是由製程端產生的PM2.5經過Salix5000吸溼潮
解(RH>95%)後形成的硫酸銨液滴,進而再釋放出酸鹼氣體導
致。經改善後不論是在機台下游或是煙道均看到了顯著的成
效。根據採樣結果,單台HT-SPM在全年全時運轉的條件下
(full run),PM2.5的排放量為0.6ton/year,若以Wet-EP處理
廢氣,不僅可以將PM2.5的排放量降低為0.06ton/year,還能
解決大部分酸鹼的問題。以F12P6為例,若HT-SPM下游全部
配置Wet-EP,則每年能減少2.73ton的PM2.5及1.44ton的硫酸
氣體,距離綠色製造更進一步,而目前Wet-EP也已經被納入
34