4.4.3 Plant Layout 4.4.4 Project Milestone
As shown in Figure 17 below, the CaF 2 sludge will be As shown in Figure 18, the supplier will take about 4
shipped by trucks from F15A or F15B, and transferred it to CaF 2 months to apply CTSP member in order to rent the land and
sludge receiving pit. Then CaF 2 sludge is transferred to Process apply construction permits. The construction will start around
area for crushing, rotary-drying, granulation, belt-drying, and 10/E in 2021 and take about 12 months to complete including
bagging. equipment installation. The operation permits may take about
8 months. Thus the operation will start up around June 2023.
Figure 17、Preliminary Layout of FRP
Figure 18、Project Milestones of FRP Scope