           4.4.3  Plant Layout                               4.4.4  Project Milestone
              As shown in Figure 17 below, the CaF 2  sludge will be   As shown in Figure 18, the supplier will take about 4
           shipped by trucks from F15A or F15B, and transferred it to CaF 2    months to apply CTSP member in order to rent the land and
           sludge receiving pit. Then CaF 2  sludge is transferred to Process   apply construction permits. The construction will start around
           area for crushing, rotary-drying, granulation, belt-drying, and   10/E in 2021 and take about 12 months to complete including
           bagging.                                          equipment installation. The operation permits may take about

                                                             8 months. Thus the operation will start up around June 2023.























                                            Figure 17、Preliminary Layout of FRP







































                                          Figure 18、Project Milestones of FRP Scope